Gattis School Road Segment 3

This project is a part of the Transportation Master plan.  Proposed improvements for Segment 3 include: widening the existing four-lane roadway to a six-lane major divided arterial, pedestrian improvements, bicycle enhancements, right and left turn bays at A. W. Grimes Boulevard and Double Creek Drive.  Median improvements to improve traffic flow and enhance safety include a raised center median and median openings at Southcreek Drive and Joyce Lane.

The design of the project has been completed and the project was bid on February 27, 2024.  The low bidder was Cash Construction and a Notice to Proceed was issued to them on August 26, 2024.  The actual construction work began on the 28th of August.  The contractor continues with the first phase of the project and expected to last until early Spring.  The total project timeline is approximately 2 years.

View Project Map (PDF)

All Gattis School Road Segments Map (PDF)

Construction Phase
Transportation
Rodriguez Transportation Group
Cash Construction
Bill Stablein
512-218-3237
bstablein@roundrocktexas.gov
Scroll to Top