 Creek Bend Boulevard Extension
Print

Description: The Creek Bend Boulevard Extension project will extend the existing four-lane divided roadway from Creek Bend Circle across Brushy Creek and Hairy Man Road to connect with Brightwater Boulevard at Wyoming Springs Drive. The project will include raised medians, sidewalks and bicycle accommodations. This project will provide north-south connection over Brushy Creek, thus increasing connectivity and reducing the reliance on IH 35 for north-south movements on the west side of Round Rock. Completion of this project will also alleviate some of the traffic on Sam Bass Road and RM 620 and will make construction of future projects on these two east-west routes more feasible by providing an alternate route.

Budget: $8,000,000 to $9,000,000

Project Manager: Leah Collier- (512) 341-3318

Project Timeline:

  • Engineering and Design-January 2012-February 2013; May 2014-August 2014
  • Geophysical and Geotechnical Studies- January 2013-May 2014
  • Bid - To Be Determined
  • Construction - To Be Determined

Project Status: 95 percent plans are complete; 100 percent plans in design; Environmental under review

Engineer: Atkins

Construction Contractor: To Be Determined

Project Map:


View Creek Bend Blvd Ext in a larger map