Why?
Increase southwest downtown's economic development potential by beautifying the area and providing new infrastructure which promotes business development
What?
Installation of new utilities (wet and dry), street furniture, lights and trees. Construction of wider sidewalks, street re-paving, on-street parking, and all other improvements to bring this area into compliance with the Downtown Master Plan.
Where?
Blair Street from W. Liberty south to McNeil Road
Bagdad Avenue from Brown Street east to Mays Street
McNeil Road from Blair Street to Bagdad Avenue
W. Liberty from Round Rock Avenue to Blair Street
When?

Project Details
- Budget - $6,080,300
- Project Manager - Leah Coffman - (512) 341-3318
- Engineer - Baker Aicklen & Associates
- Construction Contractor - TBD
Map
View SWDT - Main St., Blair St. & Bagdad Ave. in a larger map