Parks Develoment Updates Issue #6
Play for All Abilities Park - Project Complete (March 2012) Now open! Rock Hollow Park - Project Complete (March 2012) Now open! Buck Egger Park - Project Complete Opening in April! Somerset Park Status: Construction (90% Complete) Est. Completion: March...
Play for All Abilities Park - January 2012 Update
Status: Under Construction (85% complete) Est. Completion: January 2012 The Play for All Abilities Park is on schedule to open to the public February 2012 with a Grand Opening Celebration. More information on the Grand Opening event will be available...
Parks Development Updates Issue #4
Main Street Plaza Status: Completed Park Amenities: interactive water feature, art screens (along Nelson Hardware Building), stage, shade structure, seatwalls, active light system, concrete plaza, landscape areas Play for All Abilities Park Status: Under...
Christmas Tree recycling services into the New Year
The City of Round Rock encourages residents to recycle their Christmas trees on Saturday, January 2 at the Round Rock Brush Recycling Center located at 310 Deepwood Drive. Round Rock residents will get more than just a good feeling from recycling their...