Parks Develoment Updates Issue #6

Play for All Abilities Park - Project Complete (March 2012)
Now open!

Rock Hollow Park  -  Project Complete (March 2012)
Now open!

Buck Egger Park  -  Project Complete
Opening in April!

Somerset Park
Status:  Construction (90% Complete)
Est. Completion:  March 2012
Park Amenities:  renovation of playground, concrete trail, shade structure, site furnishings (picnic tables, benches, drinking fountains) and possible basketball court

Current Project Progress
Playground equipment installed, 95% of sidewalk installed, pavilion installed, basketball court 95% complete
Need to install site furnishings, playground surfacing, surface basketball court, and finish remaining sidewalk

Chisholm Valley Park
Status:  Construction (90% complete)
Est. Completion:  March 2012

Park Amenities:  renovation of playground, shade structure, +/- ½ mile of concrete trail, multipurpose rec field, site furnishings (picnic tables, benches, drinking fountains), trees

Current Project Progress
Playground area 95% complete, concrete sidewalks 95% complete, decomposed granite trail is based, multipurpose field is graded, pavilion is installed
Need to pour concrete curbs and install decomposed granite trail, install playground surfacing, site furnishings, install masonry columns on pavilion

Rabb House Redevelopment Project
Status:  Design
Est. Completion:  Design - Spring 2012

Park Amenities:  design and construction documents for the redevelopment of Rabb House (damaged in September 2010 flood)

Current Project Progress
Conceptual Master Plan is completed, will be presented to City Council on April 10th

OSPV Reuse Water Project
Status:  Design
Est. Completion:  Summer 2012

Park Amenities:  removal/replacement of existing irrigation system valves, heads, etc. to comply with reuse water requirements.  Renovation of existing irrigation system at Lakeview Pavilion area, Football Complex, Cricket Field, etc.

Current Project Progress
Utility Dept. to start mainline work and point of connections in April
Compliance repairs and time sensitive renovations tentatively scheduled for late Spring 2012
Major renovations tentatively scheduled for June/July 2012

Kensington Greenbelt Improvement Project
Status:  Design
Est. Completion:  Design - May 2012
Construction – September 2012

Park Amenities:  replacement of existing trail, playground, site furnishings and addition of pavilion structure

Mesa Village Improvement Project
Status:  Planning
Est. Completion:  Design – May 2012
Construction – October 2012

Park Amenities:  replace existing asphalt trail with decomposed granite, replace existing pavilion, and improvements to existing multipurpose field

Brushy Creek Regional Trail Gap Project
Status:  Design and Right-of-Way Acquisition
Est. Completion:  Spring 2013

Park Amenities:  +/- 2.5 miles of Brushy Creek Trail from Sonoma subdivision, across Brushy Creek, connecting to Rabb Park and AW Grimes Blvd multi-use path.  Also connects to Greater Lake Creek Trail totaling approx. 7 miles.

Current Project Progress
R.O.W. acquisition negotiations on-going
Surveying and environmental review on-going 

Comments

No Comments